Phu Quoc accelerates water projects to ensure supply for APEC 2027
To improve supplies, the province is investing in two new water supply complexes: Cua Can Reservoir and Water Plant, and Duong Dong 2 Reservoir and Water Plant. The two plants will have a combined capacity of 86,000 cu.m per day.
Construction of the Duong Dong 2 reservoir project (Photo: baoangiang.com.vn)

An Giang (VNA) – Phu Quoc Special Zone in the southern province of An Giang is speeding up construction of reservoirs and water plants despite the rainy season to prepare for the APEC 2027 Economic Leaders’ Meeting and address the island’s chronic clean water shortage.

Phu Quoc’s main water supply comes from Duong Dong Reservoir, with a capacity of 5.9 million cu.m, and Duong Dong Water Plant, which can treat 24,000 cu.m of water per day. The system serves Duong Dong, An Thoi and parts of Cua Duong and Duong To, meeting only about 30% of demand.

To improve supplies, the province is investing in two new water supply complexes: Cua Can Reservoir and Water Plant, and Duong Dong 2 Reservoir and Water Plant. The two plants will have a combined capacity of 86,000 cu.m per day.

Le Trung Ho, Vice Chairman of the An Giang provincial People’s Committee, said Phu Quoc’s selection as the host of APEC 2027 was a great honour and a major responsibility. Under a Prime Ministerial decision, 21 key projects have been identified to directly serve the event.

He stressed that water supply projects are essential to the meeting’s technical infrastructure and to residents’ daily lives. They will also help secure the island’s water supply over the longer term.

Cua Can Reservoir , invested in by the provincial Agricultural and Rural Development Project Management Board, will have a capacity of about 7.5 million cu.m and supply around 50,000 cu.m of water per day. It covers approximately 338.12 hectares. Duong Dong 2 Reservoir covers about 96.5 hectares. Both projects must be completed before May 30, 2027.

Construction gathers pace during rainy season

Cua Can Water Plant is designed to process 50,000 cu.m per day. Nguyen Lam Duc Dung, a technical officer at BIWELCO Construction Investment JSC, said the contractor was working to overcome weather-related difficulties and keep the plant on track to begin operations in late March 2027.

As of September 23, construction had reached about 20.5% of the planned workload. Work was underway on plant facilities. Some 4,000 metres of HDPE D560 pipeline was produced. Construction teams were also working on storage tanks, piling for sedimentation and filtration tanks, and the clean-water pumping station.

The next steps include foundation work, excavation for the raw-water pumping station, Larsen sheet piling at the intake, and steel reinforcement for storage tanks and the clean-water pumping station.

Worker Ho Quoc Cuong said the team was striving to meet the company’s schedule. As the site is far from residential areas, the company has provided accommodation and meals to help workers focus on the job.

Duong Dong 2 Water Plant, with a designed capacity of 36,000 cu.m per day, is undergoing site levelling and related land procedures. Trial piling has been completed, earthworks for two storage tanks have been finished, and 15.4km of the planned 33km pipeline has been installed, reaching 47.4%. The project is also due for completion before May 30, 2027.

An Giang authorities are translating directives by central agencies into specific schedules and responsibilities, implementing the Prime Minister’s Decisions No. 948/QD-TTg and No. 1679/QD-TTg. National Assembly Resolution No. 41/2026/QH16, effective from September 1, provides special mechanisms for planning, public investment, construction, land, acceptance, and payment to accelerate APEC-related projects.

The province is applying a “six clear” approach, assigning clear responsibilities, tasks, timelines and accountability, alongside a fast-track process for APEC-related paperwork. Provincial leaders are conducting regular site inspections and specialist meetings to resolve obstacles while ensuring quality, safety and transparency./.

See Also

Top leader pledges support for firms, presses tech self-reliance

The Vietnamese Party and State value entrepreneurs’ contributions, protect their legitimate rights and interests, and support them in realising their potential and achieving legitimate prosperity, General Secretary of the Communist Party of Vietnam Central Committee and President To Lam said.

Ho Chi Minh City’s economy grows 9.86% in Q3

Ho Chi Minh City recorded 9.86% economic growth in Q3, taking its nine-month expansion to 9.06%. Strong FDI inflows, resilient services and accelerated public investment are underpinning the city’s economic performance as it seeks to maintain growth momentum in the final quarter of 2026.

Nearly 149,700 new enterprises registered in first nine months of 2026

Nearly 149,700 enterprises were newly registered nationwide in the first nine months of 2026, with total registered capital reaching 1.884 quadrillion VND, up 3.2% in enterprise numbers and 32.7% in capital year on year. Average registered capital per new enterprise stood at 12.6 billion VND, up 28.5%.

Vietnam’s manufacturing sector maintains growth in September

Vietnam’s manufacturing sector continued to grow in September, although rates of expansion in output and new orders eased from those seen in August, according to the Vietnam Manufacturing Purchasing Managers’ Index (PMI) report recently released by S&P Global.

Digital platforms take Ha Tinh specialities to wider markets

More than 200 OCOP products are being promoted through digital platforms as the central province of Ha Tinh steps up efforts to expand markets for its agricultural and speciality products. By connecting producers with e-commerce platforms and organising Mega Live sessions from production areas, the province is bringing local products closer to consumers nationwide and opening up new sales opportunities.

Ho Chi Minh City advances shift to waste-to-energy treatment

More than 14,000 tonnes of household solid waste generated daily are putting pressure on Ho Chi Minh City’s collection and treatment system. At Da Phuoc Integrated Waste Management Facility, the city’s largest, a technology shift is under way to reduce landfilling and expand waste-to-energy treatment.

NA President arrives in Beijing, beginning official visit to China

Vietnam–China relations have continued to develop, particularly following reciprocal visits by General Secretary of the Communist Party of Vietnam Central Committee and President To Lam and General Secretary of the Communist Party of China Central Committee and President of China Xi Jinping.